GFT Celebrates Portal North Bridge Cutover Milestone on the Northeast Corridor
First Train Crossing Marked the Start of Revenue Service on the New Fixed-Span Bridge, Second Track Cutover Planned for Later This Year
A Major Milestone for Northeast Corridor Reliability
GFT celebrates the Portal North Bridge cutover milestone on the Northeast Corridor, marking a major step forward in rail reliability and performance. NJ TRANSIT, Amtrak, and project partners completed the first track cutover and welcomed a ceremonial first train crossing in Kearny, New Jersey, signaling the start of passenger service on the new bridge.
Following months of staged construction and carefully coordinated service adjustments that began in mid-February, the first track on the new bridge entered passenger service on March 16. The transition required precise planning to maintain operations across one of the nation’s busiest rail corridors.



Replacing a Critical Bottleneck
The approximately $1.6 billion Portal North Bridge Project replaces the 116-year-old swing bridge over the Hackensack River with a modern, fixed-span structure.
Key improvements include:
- 50-foot vertical clearance, eliminating the need for bridge openings.
- Reduced rail delays caused by mechanical failures and marine traffic.
- Improved reliability for NJ TRANSIT and Amtrak operations.
- Increased capacity to support future rail growth along the Northeast Corridor.
The new bridge removes a long-standing chokepoint and strengthens one of the most critical links in the national passenger rail network.
A second and final track cutover is scheduled for the fall. Once the second track is cut over, the transition to the new bridge will be complete, advancing a key priority of the Gateway Program and improving service for the hundreds of trains that travel this corridor each day.
GFT’s Role in Rail Systems and Program Delivery
GFT leads the Portal Partners Tri-Venture team, delivering final design for critical rail systems and infrastructure elements.
GFT’s responsibilities include:
- Track design and trackwork coordination.
- Rail signaling systems.
- Electric traction power systems.
- Coordinated rail operations planning.
- Geotechnical design and retaining walls.
GFT is also providing construction-phase services as the project advances toward full revenue service.
Beyond the bridge itself, GFT has led final engineering for the broader Portal Bridge Capacity Enhancement program. This work includes reconfiguring 2.5 miles of the Northeast Corridor and associated interlockings to improve operational flexibility and performance.
“This cutover reflects years of teamwork and disciplined planning across owner, operator, and contractor teams. GFT is proud to help deliver the rail systems that support safe operations today and a more reliable corridor for decades to come.”
Ted Bandy
Director of Rail Systems
About the Portal North Bridge Project
The Portal North Bridge is a cornerstone investment in the Northeast Corridor, supporting both current operations and future expansion. By replacing aging infrastructure with a modern, resilient structure, the project enhances reliability, reduces delays, and improves the passenger experience across the region.
Media Contact
Jill Black
Chief Marketing Communications Officer

Jill Black is a strategic, results-driven marketing and communications leader with over 20 years of experience. She has driven two major rebrands and merger and acquisition communications, spanning brand storytelling, digital strategy, thought leadership, and conference engagement to strengthen GFT's reputation and impact.
Jill Black
Chief Marketing Communications Officer
Jill Black is a strategic, results-driven marketing and communications leader with over 20 years of experience. She has driven two major rebrands and merger and acquisition communications, spanning brand storytelling, digital strategy, thought leadership, and conference engagement to strengthen GFT's reputation and impact.

Jill Black
Chief Marketing Communications Officer

Jill Black is a strategic, results-driven marketing and communications leader with over 20 years of experience. She has driven two major rebrands and merger and acquisition communications, spanning brand storytelling, digital strategy, thought leadership, and conference engagement to strengthen GFT's reputation and impact.
Featured News & INSIGHTS
Replacing a Chicago Rail Bridge While Maintaining Continuous Service

Delivering Urban Light Rail Through Alternative Project Delivery

GFT Welcomes Fuller as Transit & Rail Global Business Line Director

GFT, Clients Honored with 2026 ACEC Engineering Excellence Awards

Engineering Ingenuity: Replacing Bridge A32 and Grayland Station in Urban Chicago
East San Fernando Valley LRT: Enhancing Regional Mobility & Connectivity Using Alternative Project Delivery
Isaac Renteria, CPSM

Kim Hastings