Fairfield, Licking, and Perry Counties, OH
Buckeye Lake Dam Rehabilitation
Client: Ohio Department of Natural Resources
Our Role: Design, Construction Management

In 2015, the U.S. Army Corps of Engineers issued a grave warning about the stability of the Buckeye Lake Dam in central Ohio. The 4.1-mile-long Class I high-hazard-potential earthen embankment, more than 180 years old, did not meet dam safety requirements and was at risk of catastrophic failure. Dam failure would endanger an estimated 3,000 lives downstream of the dam and threaten 2,100 homes and businesses. In response, the Ohio Department of Natural Resources (ODNR) lowered the lake’s water level by 3 feet to winter pool level, reducing the risk of collapse, and sought ways to upgrade the dam as quickly as possible.
ODNR engaged GFT to design interim risk reduction measures (IRRM) to protect the community. GFT’s innovative solutions included an embankment stability berm, upstream of the dam, to preserve its integrity and a deep soil mix cutoff wall to stop seepage through the embankment. The team completed the IRRMs in eight months—almost a year ahead of schedule—using fast-tracked construction manager at risk (CMAR) delivery. Successful installation allowed ODNR to raise the lake’s water level to a foot below normal, boosting area businesses that depend on boating, fishing, and tourism. Our firm also served as lead designer for the dam rebuild that provides up to 100 years of protection from dam failure.
The stability berm not only protects the existing embankment, but also created a platform for workers to construct the cutoff wall. The 30-foot-wide berm runs the length of the dam and consists of approximately 400,000 cubic yards of granular fill. To build the wall, workers dug a trench 42 feet deep in the center of the berm along its entire length, while simultaneously injecting a slurry that formed a belowground barrier. This deep soil mixing method created an effective wall and minimized the risk of damage to adjacent homes during construction.
For the project’s second phase, the team designed a new buttress wall between the cutoff wall and the old dam face, to provide long-term protection against dam failure. Deep soil mixing was used to construct the wall, which runs the full length of the embankment. The top of the new dam was clad in concrete and topped with grass and a paved path to create a lakeside promenade and offer vehicle access for inspections. The new dam allowed ODNR to return water levels to normal, shoring up the area’s economy, and providing long-lasting protection for Buckeye Lake that meets dam safety requirements and community expectations.
Key Features
- 30-foot-wide stability berm protects the existing dam embankment and facilitated construction of the deep soil mix cutoff wall.
- 24-inch-wide deep soil mix cutoff wall extends 42 feet belowground to stop seepage and preserve dam integrity.
- New 4.1-mile-long buttress wall has design life of up to 100 years.
- Paved path on top of new dam offers vehicle access for future dam maintenance and repair.
Outcomes
- Upgrades bring dam into compliance with dam safety requirements.
- Return to full lake depth supports boating and fishing to revitalize the economy.
- CMAR delivery and aggressive schedule shortened project timeline by two years.
- Grand Award, 2020, American Council of Engineering Companies (ACEC) Ohio, Engineering Excellence Awards.
- National Recognition Award, 2020, American Council of Engineering Companies (ACEC), Engineering Excellence Awards.
- National Rehabilitation Project of the Year, 2019, Association of State Dam Safety Officials (ASDSO) Annual Awards.
Featured Projects

Thornwood Crossing Connector, Roundabout & Bridge Replacement

Illinois’ Central Tri-State Tollway (I-294) Reconstruction

Ohio Statewide GIS Solutions Powered by Esri Technology

Houbolt Road Extension and Diverging Diamond Interchange (DDI)

Merchants Bridge Main Span Truss Replacement & East Approach Retrofit

CREATE P3 Forest Hill Flyover Bridge and 71st Street Grade Separation

NREL EV Infrastructure Design and Siting Assessment Tool

Devil’s Kitchen Dam Auxiliary Spillway Modifications

Zero-Emission Fleet Planning for the Chicago Transit Authority (CTA)

Commercial Bakery Wastewater Pretreatment Systems

Meat Production Facility Wastewater Pretreatment System

Chicago Transit Authority Program Management

I-90 Kennedy Expressway Westbound Reconstruction

Union Pacific Railroad Bridge 3.49 Over Ashland Avenue Replacement
Featured News & INSIGHTS
Connecting Chicago to the Obama Presidential Center

GFT, Clients Honored with 2026 ACEC Engineering Excellence Awards

John Sadler, PE

Ryan Stephen, PE