Harrisburg, PA
I-81 River Relief Route Emergency Design
Client: Pennsylvania Department of Transportation
Our Role: Analysis, Design, Rehabilitation, and New Construction

In 2013, a tanker truck carrying 7,500 gallons of diesel fuel overturned on the I-81 northbound ramp to U.S. Route 22 in Harrisburg, and a massive fire shut down one of the busiest sections of the interstate.
Searing heat severely damaged the bridge, warping the metal guide rails and incinerating portions of the deck. At the request of the Pennsylvania Department of Transportation (PennDOT), GFT immediately sent a team to the crash site to evaluate the structural stability of the overhead bridge.
Before the smoke had cleared, the team began analyzing the damage and determining how to remove the old bridge and design the replacement structure. As the original designers of the nearly 40-year-old bridge, our firm supplied the information needed to start the design process promptly. This immediate response aided in the rapid replacement of the overhead structure and rehabilitation of the ramp bridge, which helped PennDOT restore the entire interchange within seven months of the fire.
Our structural engineering team conducted analysis of bridge elements based on the contractor’s proposed demolition sequence and calculated crane pick weights for each stage of the demolition. Due to the long lead time required to fabricate bearings, our structural engineers were asked to develop drawings for replacement bearings for both the ramp bridge and the U.S. Route 22/322 eastbound bridge.
Our firm also redesigned and detailed the cross girders for the new bridge, which included reviewing shop drawings for the refabrication of the steel superstructure. Additionally, we developed repair procedures for the Ramp B bridge following PennDOT’s forensic analysis of the steel superstructure.
Construction services included the review of a crane pad for the demolition of the remaining portion of the fire-damaged bridge and erection of the new superstructure. Our firm also developed construction drawings for the Ramp B structure and reviewed the:
- Work platforms.
- Formwork.
- Demolition and erection analysis.
- Crane pad.
- Stay-in-place (SIP) bridge forms.
- Strip seal dams.
Key Features
- Structural analysis guided demolition of damaged overhead bridge.
- Replacement bearing and cross girder redesign provided effective superstructure support.
- Repair procedures developed for restoration of Ramp B bridge.
Outcomes
- Reopened I-81, serving 85,000 motorists daily, within days.
- Rapid response enabled quick start to demolition and design.
- Restored severely damaged interchange within seven months.
- Grand Conceptor Award, 2015, American Council of Engineering Companies (ACEC) of Pennsylvania, Diamond Awards for Engineering Excellence
- National Recognition, 2015, American Council of Engineering Companies, Engineering Excellence Awards
Featured Projects

Thornwood Crossing Connector, Roundabout & Bridge Replacement

Meadowlands Pedestrian Bridge Expansion at MetLife Stadium
Featured News & INSIGHTS
Replacing a Chicago Rail Bridge While Maintaining Continuous Service

Leveraging the Power of Bridge Condition Assessments

From Roadway to Rail Trail: Adaptive Reuse of the Mount Carbon Bowstring Truss
AI in Action: Practical Applications for Bridge Engineering

GFT, Clients Honored with 2026 ACEC Engineering Excellence Awards

In The News: Cutting-Edge Transportation Technologies in Action

John Bergman, PE

Salvatore “Sal” Costanzo