Kern County, CA
Lake Isabella Dam Safety Modification
Client: US Army Corps of Engineers, Sacramento District
Our Role: Geotechnical Engineering

Lake Isabella offers Southern Californians 568,000 acre-feet of water-based recreation opportunities and serves as a primary water source for Kern County residents. The lake was formed in 1953 when the U.S. Army Corps of Engineers (USACE) built the earthfill embankment Isabella Dam, consisting of a main and auxiliary dam, across the lower Kern River and Hot Springs Valley. Located 40 miles northeast of Bakersfield, the dam and lake provide flood-risk management for 300,000 downstream residents and irrigation for 350,000 acres of farmland.
Due to safety concerns, the lake’s volume was restricted to approximately 60% of total capacity for years, impairing the USACE’s ability to accommodate spring runoff from the Sierra Nevada snowpack. Despite the low water levels, the unpredictability of extreme weather events made flooding a potential threat to surrounding farmland and downstream communities.
The risk of overtopping, combined with seismic concerns and seepage issues, elevated the dam’s risk classification and spurred the USACE to undertake a three-phase dam safety modification project. The agency selected GFT to support phase two, the main effort to modify the dams and spillways.
To reduce the risk to life and property from flood events, earthquakes, and seepage, phase two of the Lake Isabella Dam project included:
- Raising both dams – main and auxiliary – by 16 feet.
- Improving the filtering and drainage systems on both dams.
- Adding a new 900-foot emergency spillway.
One of the project’s most visible aspects is the new three-story labyrinth weir in the emergency spillway. The accordion-like shape maximizes the concrete weir’s surface area, slowing the water flowing in the spillway and resulting in a controlled release.
Tapping into our best-in-class dam and levee engineering expertise, GFT provided geotechnical engineering services during construction when an immense amount of materials were moved to create the dam addition and new spillway. Crews excavated over 3.5 million cubic yards of earth to make room for the new spillway and reinforce the main and auxiliary dams with over 67,000 cubic yards of concrete and almost 2.5 million cubic yards of rock.
GFT provided earthwork construction observation, including excavation, fill placement, moisture conditioning, and compaction, to confirm design specifications and design requirements were met. We observed work activities at the borrow site and oversaw blending existing materials with the borrow soils, including identifying undesirable soils that did not meet the specifications.
Key Features
- A wider and deeper emergency spillway supplements the existing service spillway.
- Reinforcement materials were excavated onsite, reducing the need to unload materials from elsewhere.
- The weir’s sawtooth shape slows the rushing water in the emergency spillway.
Outcomes
- Makes complex scientific concepts accessible to diverse audiences.
- The modifications addressed overtopping, seepage, and seismic concerns.
- USACE lowered the dam’s risk level from “highest urgency and risk” to “low urgency.”
- Operating the lake at full capacity boosts the local economy by increasing recreation opportunities that attract tourists.
- Operating at capacity also increases the amount of electricity produced by the privately owned hydroelectric plant on the main dam’s south side.
Featured Projects

Valley Center North County Emergency Water Storage Project

Priest Rapids and Wanapum Dam Safety Engineering Services

Rehabilitation of Six Thunder Bay Structural Culverts

Gambo Bridge Replacement at Naval Support Facility Dahlgren

Risk-Informed Decision-Making at Union Valley Dam

Orange County Coastal Storm Program Management

Garden State Parkway Shoulder Widening Milepost 30-35

Devil’s Kitchen Dam Auxiliary Spillway Modifications

Hawaiian Dam Safety Seismic Hazard Assessment

Fish Passage Design at the Adam T. Bower Memorial Dam
Featured News & INSIGHTS
Searching for Water: Engineering Solutions for the Colorado River’s Survival

How Updated Data and Regional Detention Are Reducing Flood Risk in Texas

UPCOMING 10/15: The Good, the Bad & the Biosolids: Carlisle’s Path to Class A

Rethinking Flood Risk: Identifying and Reducing Impacts Without Dams

Dina Hunt Named to Society of Women Engineers’ 2026 Women Engineers You Should Know

Aimee Corn Elected to the USSD Board of Directors

Abe Khademi, PEng

Amy Dziuk, PE, CFM