Gould, CO
North Michigan Creek Dam Rehabilitation
Client: Colorado Department of Natural Resources, Colorado Parks and Wildlife
Our Role: Design and Construction Management

North Michigan Creek Dam, nestled in the jagged peaks and thick, wooded areas of State Forest State Park, is a hidden gem in northern Colorado. The creek’s waters overlie glacial deposits, attracting anglers keen on catching kokanee salmon, Arctic char, and rainbow trout. Built in 1963 by Colorado Parks and Wildlife (CPW), the 75-foot-high and 400-foot-long embankment dam sits at an elevation of nearly 9,000 feet and has a storage capacity of more than 1,100 acre-feet at normal pool.
CPW, which owns over 120 dams, regularly monitors, inspects, and improves its assets. During a routine dam safety inspection of the North Michigan Creek Dam, CPW found that seepage levels from the right abutment exceeded acceptable limits, thus prompting a declaration of emergency conditions and a restriction of the reservoir’s water level. The situation underscored the urgent need for a comprehensive rehabilitation strategy to ensure the dam’s integrity and functionality.
GFT provided design engineering services for Phase 1 of the rehabilitation program to address the dam’s seepage issues and enhance its structural resilience.
Phase 1 design began with updating the dam breach analysis, as required by the state’s dam safety program. Working closely with CPW engineers and state park staff, GFT completed hydrologic analyses using the then-newly released 2018 Colorado-New Mexico Regional Extreme Precipitation Study data. Estimating probable maximum precipitation is critical to designing spillways that protect dams against extreme weather events.
Historically, the dam had been classified as a low-hazard potential dam, meaning minor damage to non-critical infrastructure could be expected in the event of dam failure. However, an updated dam breach analysis by GFT indicated that several roads and access to private residences would suffer damage, increasing the dam’s hazard potential. As a result, the dam was reclassified as a significant-hazard potential structure. Deficiencies were also identified in the existing concrete chute spillway and earthen embankment.
Rehabilitation measures included:
- Replacing the concrete-lined spillway, which sat on an erodible foundation.
- Replacing the intake structure using a slide gate and operator grade beam.
- Replacing the pedestrian bridge.
- Installing a cured-in-place pipe lining and filter diaphragm for the low-level outlet pipe.
- Improving the outlet channel.
- Installing a right abutment seepage collection system, including instrumentation for monitoring.
Recovered materials, such as demolished concrete from the spillway and intake structure, were recycled to reduce environmental impacts and used to develop a fish habitat within the reservoir.
Mid-project, CPW opted to convert the project delivery from design-bid-build to construction manager/general contractor (CM/GC), making this the first-ever application of alternative delivery for a Colorado Department of Natural Resources construction project. The CM/GC delivery enabled the team to streamline the design-construction approach into a construction package that could be completed in a single season. The project schedule and budget were maintained despite the changes in the delivery method.
GFT conducted a potential failure modes analysis (PFMA) focused on the proposed solutions of the dam rehabilitation design. After an initial potential failure mode screening, the credible failure modes were carried forward to a PFMA workshop facilitated by GFT. This risk-based approach led to a more complete understanding of the downstream consequences and risks associated with specific potential dam deficiencies and helped prioritize analyses, actions, and alternatives that reduced the highest risks.
During Phase 2, GFT provided quality assurance during construction to ensure adherence to design specifications. As engineer of record, we provided full-time, on-site quality assurance, managed submittals, proactively resolved construction issues, and developed as-constructed drawings.
Key Features
- Right abutment seepage collection system.
- New concrete-lined spillway.
- Fish habitat made from recovered spillway and intake structure materials.
Outcomes
- Makes complex scientific concepts accessible to diverse audiences.
- Enhancing the dam’s safety and operational capacity protects local communities and ecosystems.
- Switching from design-bid-build to CM/GC delivery streamlined the project approach and enabled the dam safety improvement to be completed in one season.
- Incorporating a PFMA in the dam rehabilitation design helped prioritize actions to reduce the highest risks.
- Engineering News-Record, 2022, Mountain States Best Projects, Best Project Water/Environment



Featured Projects

Houston Area Water Supply System Program Management

Valley Center North County Emergency Water Storage Project

Priest Rapids and Wanapum Dam Safety Engineering Services

Rehabilitation of Six Thunder Bay Structural Culverts

Gambo Bridge Replacement at Naval Support Facility Dahlgren

Risk-Informed Decision-Making at Union Valley Dam

Orange County Coastal Storm Program Management

Garden State Parkway Shoulder Widening Milepost 30-35

Ocean Outfall Legislation Program and Construction Management Services

Wastewater Consent Decree Program Management and Construction Management Services

Devil’s Kitchen Dam Auxiliary Spillway Modifications

Surface Water Supply Project Segment C2 Program and Construction Management
Featured News & INSIGHTS
Searching for Water: Engineering Solutions for the Colorado River’s Survival

How Updated Data and Regional Detention Are Reducing Flood Risk in Texas

UPCOMING 10/15: The Good, the Bad & the Biosolids: Carlisle’s Path to Class A

Rethinking Flood Risk: Identifying and Reducing Impacts Without Dams

Dina Hunt Named to Society of Women Engineers’ 2026 Women Engineers You Should Know

GFT Expands Alternative and Collaborative Project Delivery Leadership with Steven Grech

Yovani Zelaya, PE

Abe Khademi, PEng