Perth Amboy and South Amboy, NJ
Raritan River Bridge Replacement
Client: New Jersey Transit Corporation (NJ TRANSIT)
Our Role: Design

The Raritan River Bridge carries approximately 10,000 commuters every weekday on the NJ TRANSIT North Jersey Coast Line, a vital passenger rail connection between coastal New Jersey and New York City. It also carries 2 million tons of freight annually on Conrail trains. Built in 1908, the existing bridge, known locally as the River Draw, was damaged by Superstorm Sandy in October 2012. Replacing the bridge became a top priority for NJ TRANSIT.
GFT, in a joint venture with Hardesty & Hanover, provided conceptual and preliminary design for the Raritan River Bridge Replacement Project for NJ TRANSIT. Supported on a steel, multi-girder superstructure with pier spacing roughly 95 feet apart, the new bridge will be 34 feet wide (10 feet wider than the original) to place dual tracks 14 feet apart and include two 2-foot-wide maintenance walkways. The ballasted deck, approach track, and fixed spans will have a continuous welded rail.
Substructure construction includes 84, 8’ diameter drilled shafts up to 240 feet deep, comprising 28 substructure units with over 3,500 cubic yards of concrete. The approach span superstructure construction consists of 24 spans of six steel girders per span, with a steel plate ballast pan. Additional work includes ground improvements leading up to the rail bridge structure, drainage, grading, retaining walls, and other miscellaneous construction.
Construction of a new movable lift drawbridge upstream of the existing swing structure improves rail system operations and allows river access for large freight and cruise ships. Additional enhancements include raising the new bridge’s profile above the 100-year floodplain for protection during powerful tidal surges and using corrosion-resistant materials that enable the structure to withstand saltwater immersion. Other design features help improve resilience, including:
- New reinforced concrete piers with galvanized steel reinforcement.
- Galvanized steel superstructure.
- Drive motor and electrical controls.
- Vertical adjustment of the existing track.
- Electrical power relocation.
Commuters and other rail customers will benefit from improved connections between New York job centers and New Jersey shore communities.
Key Features
- Provides adequate structural capacity to comply with current code requirements.
- Optimized design for rail traffic speeds up to 60 miles per hour.
- Accommodates heavier freight trains with railcars up to 286,000 pounds.
Outcomes
- Creates more resilient infrastructure to severe weather.
- Minimizes loss of service on the North Jersey Coast Line during and following storms.
- Improves marine navigation beneath the bridge.
- New Jersey Chapter of the American Concrete Institute, 2024, Grand Award
- New Jersey Alliance for Action, 2021, New Jersey’s Leading Infrastructure Project Award

Featured Projects

Interstate 4 at SR 557 Interchange Design-Build

Thornwood Crossing Connector, Roundabout & Bridge Replacement

Illinois’ Central Tri-State Tollway (I-294) Reconstruction

Meadowlands Pedestrian Bridge Expansion at MetLife Stadium

North Wilkesboro Speedway Pedestrian Bridge

Pennsylvania Turnpike Commission GeoBIM Implementation

Gambo Bridge Replacement at Naval Support Facility Dahlgren

Gardiner Expressway Section 5 Detailed Design

Garden State Parkway Shoulder Widening Milepost 30-35

Harry W. Nice/Thomas “Mac” Middleton Bridge Replacement

Houbolt Road Extension and Diverging Diamond Interchange (DDI)

Merchants Bridge Main Span Truss Replacement & East Approach Retrofit
Featured News & INSIGHTS
Replacing a Chicago Rail Bridge While Maintaining Continuous Service

Beyond the Control Room: How Traffic Operations are Shaping Transportation Systems in Real Time

GFT, Clients Honored with 2026 ACEC Engineering Excellence Awards

ACEC Recognizes GFT, Clients With 15 Engineering Excellence Awards

Engineering Ingenuity: Replacing Bridge A32 and Grayland Station in Urban Chicago
From Roadway to Rail Trail: Adaptive Reuse of the Mount Carbon Bowstring Truss
John Bergman, PE

Brian Seip, PE, CxA, LEED AP BD+C, CEA, REP, NCTI, ENV SP