Pennsylvania
Substation Expansion Supports Data Center Energy Demand
Client: Confidential
Our Role: Full-Service Engineering Design & Installation Support

The client required a significant expansion of an existing 500 kV substation to increase system capacity, integrate new high-voltage infrastructure, and support growing load demand, including a direct connection to a data center. The project involved complex design within an energized yard, requiring careful coordination to maintain system reliability while accommodating new equipment, reconfiguring existing infrastructure, and meeting aggressive schedule and budget targets.
GFT provided full-service engineering design and support for the installation of a new 750 MVA 500/230 kV transformer bank (three 250 MVA single-phase units) and associated substation expansion. The design incorporated a breaker-and-a-half scheme with new 500 kV breakers, additional 230 kV infrastructure, and transmission line terminations to the new data center.
Our team delivered a comprehensive set of engineering services, including detailed electrical design, physical layout, and system studies, while also supporting critical civil and site development elements. GFT carefully coordinated the integration of new equipment into the existing energized substation, ensuring constructability, safety, and minimal operational disruption. In addition, GFT provided grounding design, geotechnical coordination, surveying, grading design, and drainage system redesign to support the expanded footprint. With more than 25,000 engineering hours delivered, the project was completed ahead of schedule and under budget. GFT’s integrated, multidisciplinary approach enabled the successful delivery of a complex substation expansion while maintaining system reliability and optimizing project performance.
This project represents one of GFT’s most recent and significant substation design assignments, involving a major expansion of an existing 500 kV substation for connection of a major data center for a hyperscaler.
Key Features
- Three 250 MVA 500/230 kV single-phase transformers.
- Three 500 kV circuit breakers.
- One 230 kV circuit breaker.
- Three 500 kV CCVTs and three 230 kV CCVTs.
- Five 500 kV disconnect switches and one 230 kV disconnect switch.
- Six 500 kV surge arresters and three 230 kV surge arresters.
- One 500 kV H-frame structure and one 230 kV H-frame structure.
- Seven relay and breaker control panels.
- Removal of existing 500 kV CCVTs and wave trap.
- Addition of a new low-side line terminal.
- Installation of substation fencing, gate, and security upgrades.
Outcomes
- Updated one-line and three-line diagrams.
- Revised schematic and wiring drawings.
- Panel layouts and front-view drawings.
- Supervisory control and data acquisition (SCADA) system updates with new data points.
- AC and DC system studies.
- Bill of materials and equipment nameplate updates.
- Circuit, conduit, and drawing list revisions.
- Physical layout updates.
- Lightning protection, grounding, and photometric studies.
- Yard lighting plan for expanded areas.
Featured Projects

Modernizing Building Systems for Long Beach Water Department Operations

P.S. 341Q Brings Flexible, Resilient Learning Spaces to Hunter’s Point

P.S. 47Q Chris Galas School Modernization and Expansion

27th Avenue MRF Upgrades Advance Phoenix’s Zero Waste Vision

Adler Planetarium Cosmology Gallery Exhibit Design

Dunkirk Park Tennis Complex Design and Site Engineering

New Delaware State Police Troop 6 Headquarters

Miami Beach Hostile Vehicle Attack Vulnerability Assessment
Featured News & INSIGHTS
Architecture Career Insights: Perspectives from Practicing Architects

Climate Risk Analysis for Buildings and Infrastructure

Beyond Hollywood: The Reality of Modern Fire Protection

From Transportation Challenge to Civic Destination: Springfield’s Intermodal Hub
In The News: Strategic Design Insights for Justice Facility Security

In The News: Lasta Advocates for Accessibility-First Design

Ray Everett, AIA

Mandar Manjarekar, PE, PMP