Valley Center and Pauma Valley, CA
Valley Center North County Emergency Water Storage Project
Client: Valley Center Municipal Water District
Our Role: Construction Management and Office Engineering Support

Valley Center Municipal Water District (VCMWD), in coordination with Yuima Municipal Water District (YMWD) and San Diego County Water Authority (SDCWA), launched a comprehensive program to address longstanding vulnerabilities in a shared rural water supply system. Aging pipelines, limited redundancy, and outdated pump station infrastructure left Valley Center and Pauma Valley communities exposed to service disruptions during wildfires, earthquakes, and power outages. GFT provided construction management and office engineering support throughout program delivery, coordinating closely with VCMWD’s inspection team to sequence work across district boundaries, maintain compliance with SDCWA funding requirements, and manage documentation critical to keeping the program on track.
Key Features
- Installation of 3,800+ linear feet of 12-inch PVC pipeline along Lilac Road and Muutama Road to enable cross-district emergency water transfers.
- Removal of 430 linear feet of undersized 6-inch asbestos cement pipe.
- New flow control stations at Halcones and Muutama for pressure zone management and real-time water routing.
- Pump station modernization at San Gabriel and Lilac Pala, including new vertical turbine pumps, discharge piping, flow meters, and surge tanks.
- Electrical upgrades including new San Diego Gas & Electric switchgear, distribution gear, and variable frequency drives.
- Full SCADA system replacement for enhanced monitoring and operational control.
- Two trailer-mounted backup generators with automatic transfer and bussing systems for grid-independent operation.
Outcomes
- Established a reliable emergency water distribution system capable of cross-district transfers during regional crises.
- Reduced system vulnerability by eliminating deteriorating asbestos cement pipe.
- Improved pressure zone control and operational flexibility across district boundaries.
- Ensured continued pump station operation during grid outages through dedicated backup power.
- Strengthened long-term water security for farms, ranches, and residents in Valley Center, Pauma Valley, and surrounding communities.







Featured Projects

Houston Area Water Supply System Program Management

Palos Verdes Recycled Water Pipeline and Lago Seco Pump Station Design

Valley Center North County Emergency Water Storage Project

Gambo Bridge Replacement at Naval Support Facility Dahlgren

Ocean Outfall Legislation Program and Construction Management Services

Wastewater Consent Decree Program Management and Construction Management Services

Surface Water Supply Project Segment C2 Program and Construction Management

Tunnel Boring for WHCRWA’s Major Water Supply Project

Hopewell Water Treatment Plant Industrial Pump Station and Chemical/UV Facility

Lehigh County Authority Water Main Replacement
Featured News & INSIGHTS
Searching for Water: Engineering Solutions for the Colorado River’s Survival

How Construction Management and Inspection Improve Water Infrastructure Projects

UPCOMING 10/22: Taking Back Control: Managing Cost and Risk Through Collaborative Delivery

UPCOMING 11/12: PFAS in 2026: From Detection to Decisions

Brown Receives 2026 George Warren Fuller Award From AWWA

In the News: WHCRWA Honors GFT’s Wayne Ahrens for 25 Years of Service

Yovani Zelaya, PE

Abe Khademi, PEng